Internal hydrogen infrastructure in Bulgaria - Studies
Project 101287437 - 10.3.2-BG-S-M-25-PCI 10.3.2 – Studies
Description of the Project: The project Internal Hydrogen Infrastructure in Bulgaria - Studies covers pre-investment activities, namely preparation of a feasibility study; spatial planning and investment design, including development of route options; implementation of environmental procedures and carrying out archaeological surveys.
It is co-financed under the Connecting Europe Facility (CEF) and is the first step of implementation of Project of Common Interest (PCI) 10.3.2 Internal hydrogen infrastructure in Bulgaria towards the Greece border.
PCI 10.3.2 is part of the current EU list of Projects of Common Interest and Projects of Mutual Interest and comprises of bi-directional hydrogen transmission infrastructure, including a pipeline of 250 km approximate length and two new compressor stations of indicative total compression capacity about 48 MW. PCI 10.3.2 will provide a total hydrogen transmission capacity of approximately 0.9 Mt/y (80 GWh/d).
Main activities:
Activity 1: Preparation of a Feasibility study
Activity 2: Spatial planning and investment design activities
Activity 3: Archaeological surveys
Expected results: As a result of implementation of this project, the necessary technical and environmental studies will be completed and a technical design will be prepared that will enable Bulgartransgaz EAD to proceed with the next steps of construction of internal hydrogen transmission infrastructure in Bulgaria towards the Greek border.
Total project value: € 9 122 500
Grant amount: 4 561 250 (50%)
Start: 16 March 2026 / End: 15 November 2028
Current status of the project:
- February 2026 – The project has been approved for grant funding under the Connecting Europe Facility
- June 2026 – A Grant agreement has been signed with CINEA (the granting authority).
- Preparation for a Feasibility study
Additional information:
Information regarding the public procurements for project activities can be found in section Buyer profile Bulgartransgaz EAD within the Centralized Automated Information System "Electronic Public Procurement" (CAIS EOP) on Bulgartransgaz EAD website.
The project for construction of internal hydrogen infrastructure in Bulgaria towards the Greece border is supported by the European Commission, which has included it in all lists of approved to date Projects of Common Interest (PCI) of the EU in accordance with Regulation (EU) 2022/869.
Information about PCI 10.3.2 Internal hydrogen infrastructure in Bulgaria towards the Greece border can be found here.